The Percent Complete amounts used on Job Cost reports can be input by you (through Job Estimates) or calculated based upon other data. If you have input a percent complete value that is not greater than 100%, that value is used in all calculations. Some reports show both the input percent complete value and the calculated percent complete value.
The Percent Complete value can be calculated based on quantity, hours, or dollars.