This question is asked to determine the level at which the cost at completion calculation will be made. No matter which level is used, the results are added together to determine over/under billings for the total job.
This question is asked only on the Composite Unit Cost, Job Cost Detail, Job Hours, Labor Productivity, Percent Complete, and the Unit Cost reports.
The default for this question varies by report. Refer to Percentage Complete (Calculation 2) for more information regarding this Standard Calculation.
Alert
If there is no percent complete or final cost at the selected level, then the percent complete is calculated at the next level as outlined in the Standard Percent Complete (Calculation 2).
See Also
Job Cost Report and Questions Matrix