Composite Unit Cost Report - JC

Make the following menu selections to display this tab:

Job Cost—Reports—Job Cost Reports—Composite Unit Cost

Use this page to print the Composite Unit Cost report.

This report can be printed as part of a Series of Reports.

ClosedReport Description

The Composite Unit Cost Report is used to list unit costs for an entire phase or activity. This total unit cost is calculated by adding together all Cost Types within the Cost Activity or  Phase, then dividing the costs by the quantity completed.

Examples

Suppose you set up a Cost Activity for a slab-on-grade. You set up three costs records such as labor, material, and equipment, for the costs required to put the slab in place. The composite unit cost would give you the total unit cost of the slab.

Suppose you set up a Phase for a water line. The phase comprises several cost activities: trench excavation, laying the pipe in the trench, and restoration of the ground. By combining these activities and their respective costs, then dividing by the total feet installed, you receive a composite cost for pipe per foot, with the unit of measure for the phase as FEET.

To calculate the Unit Cost, you must select the quantity on which the unit cost calculation will be based. For example, suppose an activity contains a labor cost record with an actual completed quantity of 200 square feet. Suppose the activity also contains a material cost record with an actual completed quantity of 30 cubic yards.

You will need to choose which quantity will be used for which calculation. You can use the quantity from the labor record at 200 square feet, or you can use the quantity from the material record at 30 cubic yards. Alternatively, you can use the quantity from the phase record. This is the only report that uses the phase unit of measure.

The report is used by Project Managers and Field Managers to control a job in progress. Estimating personnel can use the report to determine current unit costs.

NOTE that you can print this report on a monthly basis after all costs and quantities have been updated. If you update costs and quantities on a weekly basis, you can print the report weekly.

ClosedTo Print the Report

Refer to Job Costing Reports Questions or the Reports Questions Matrix for more information about the questions.

  1. From the Job Cost menu, select Reports—Composite Unit Cost.
  2. Click Select EntitiesCompanies. Select the entitiescompanies for which you want to print the report and click Save.
  3. From the Cut Off Date field, use the electronic calendar to select a date, if desired. The default cut off date is the future date of 12/31/9999.
  4. Select an option for Include Jobs.
    Options are: Open and Closed (default), Open, Closed.
    If you select Closed, enter From and Thru dates in the new fields that appear.
  5. (Optional) For the various From and Thru fields (for Job, Phase, and Cost), use the Lookup icon for each field to enter a starting and ending entry for the range.
    To run the report for only one Job, Phase, or Cost Type, select the same entry for the From and Thru fields.
  6. Select check boxes for all cost categories you want to include on the report. Options include: All (default), Admin, Labor, Equipment, Material, Subcontract, Other.
  7. At Include which cost activities, select an option:
    All (default)
    All activities with postings between
    Only activities with postings between.
  8. Select a printing format for the report:
    Job totals, phase totals, and cost activity detail (default)
    Job totals only
    Job totals and phase totals
    Job totals and cost activity detail.
  9. For the next selections, check or clear check boxes, select buttons, or select from a drop-down list, as applicable, to define how you want the report to print.
  10. At New page for each job - The default is unchecked. Check the box if you want to print a new page for each job.
  11. At Calculate projected variance only if % complete is greater than the specified % - The default is checked and the default percentage in the field is 15.00, which is used in the calculation. Accept the default percentage, change the percentage, or uncheck the box and do not use this calculation.
  12. At Print only items with a current variance over/under JTD budget by the specified %  - The default is unchecked. Check the box and enter a percentage if you want the system to print these items in the report.
  13. At Include which cost information first choose to print one of these two options: Date Range (default) or None.
    Then, for Date Range, enter a From Date and a Thru Date.
  14. At Print a second line - Check the box to print
  15.  Select jobs by code - When checked, a list of User Codes with Lookups appear so that you can select one or more active Job Cost User Codes to report on. Refer to the list of Default User Code labels for Job Cost for more information.
  16. At Labor and equipment hours - Select an option to use for reporting of labor and equipment hours. Options are:
    Units Per Hour (default)
    Hours Per Unit
  17. At Begin % complete calculation with - Select an option to specify how you want to begin the percent complete calculation:
    Cost Activity Input (default)
    Job Input
    Qty/Hrs/Dollars Calculation
  18. At Include unapproved transactions - Check the box to include unapproved transactions in the report. Uncheck to report on only approved transactions.
  19. Select one of the following report printing options:
  1. Click Print. If you selected Create Spreadsheet, you are prompted to open or save the report Excel file. Otherwise, the report opens in PDF format.

See Also

Reports Introduction