Job Costing Reports: Calculate projected variance (Question 9)

This question offers the option for the system to calculate and include the projected variance percent for cost activities that have a percentage of completion greater than the percentage that you are prompted to enter. Variance calculations are based on the assumption that future costs will behave in the same way as previous costs; therefore, we recommend that you do not calculate variance until you have at least completed start-up work on an activity.

The default for this question is that the check box is selected, and 15.00 percent.

See Also

Reports Introduction

Job Cost Report Questions

Job Cost Report and Questions Matrix