Open topic with navigation
        
        Go Live Overview
        This section covers concepts and processes that apply 
 to preparing your property to go live. Once you have completed your policy, 
 global, property and resident set up you are ready to move to the final 
 transition stage. 
        This process happens in two phases—Preliminary 
 Go Live and Go Live. The preliminary phase is a very important safeguard 
 process that is strongly advised to run before attempting the final go 
 live phase. During preliminary go live, the system generates a Go Live 
 Exceptions report that alerts you to any items that have not been properly 
 set up, required or otherwise relevant items. These items may not prevent 
 final go live processing, however are items that you should give consideration 
 to. The final go live process transitions your property from setup 
 status to daily processing status. 
        
             Note
Note
        As a prerequisite to running either the preliminary or 
 final go live processes, you must have already completed your policy, 
 global, property and resident/tenant setup activities. Refer to Setup 
 Sequence for complete details. 
         Critical Fields
Critical Fields
        
        
            Critical fields are set during the final Go Live process. 
 For this reason, it is highly recommended that you make a back up copy 
 of your data prior to running final go live. The following fields represent 
 some, but not all, of the fields that are set during this process:
            
                - Last Begin of Day
- Last End of Day
- Current Accounting Period
- Go Live Flag
- Go Live Date
- Date Last Charged
- Charge Active Flag
- Next Due Date
                 Note
Note
            The Next Due Date is set to NULL for future residents 
 (those with a Resident Status 
 of A, V, X or L) so they can be charged upon move-in. 
         
         Important Dates
Important Dates
        
        
            Current Accounting Period
            The current accounting period is critical date 
 to consider. Prior to going live, verify that the Current 
 Acct Period field on the Properties 
 Tab is showing the accounting period for which the property setup 
 was completed. 
            If going live at month end, then the current accounting 
 period should be the month before you go live. For instance if you are 
 going live as of September 1, then your current accounting period should 
 be August 1. If going live mid-month, then your current accounting period 
 should be the month you are currently in. For instance if you are going 
 live in the middle of September the current accounting period would be 
 September. The Current Acct Period field displays 
 the active general ledger accounting period for the property and is updated 
 during month end processing. 
            Go Live Date
            An accurate Go Live date is very important. The 
 Go Live date must be the day before the first date that daily processing 
 will commence; for instance if daily processing will begin on 06/01/2006, 
 then your Go Live date is 05/31/2006. 
         
        See Also
        
        Go Live Tab
        
        To 
 Run Preliminary Go Live
        
        To Run Go 
 Live
        
        Special 
 Overview
        
        Special 
 Overview - Commercial Properties